StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

R.I.P. Big Transmission, We Hardly Knew Ye

6/2/2016

1 Comment

 
I'm late for the funeral!  Ran across this article yesterday when searching for something totally unrelated, but it speaks so much truth, I couldn't dismiss it.  Back in September of last year, utility rag Fortnightly ran an article headlined, "The Rise and Fall of Big Transmission:  The alternatives may make more sense."  Author Steve Huntoon chronicles the big transmission building phase that was created by Congressional action to provide incredible financial incentives for Big Transmission.  In the Energy Policy Act of 2005, Congress tasked the Federal Energy Regulatory Commission with creating a system to award incentives to transmission builders, such as double digit returns, the ability to collect project costs in rates during construction, guaranteed recovery in the event a Big Transmission project was abandoned, and many more (I'm not going to list them all here because only utility rate geeks would understand them all without lengthy explanation).  Creating incentives to build more transmission was a Congressional knee-jerk to the 2003 northeast blackout.  Nevermind that a complicated, expansive transmission system was to blame for the blackout, industry lobbyists spun the blackout its clients created through mismanagement into a huge financial windfall.  And the Big Transmission building boom began.

Huntoon walks the reader through the bad ideas that sprang from utility greed, analyzes why many of them failed, and applies his analysis to the remaining Big Transmission bad ideas to demonstrate why they, too, must fail.

And he does it in an entertaining and easily understood fashion.  Big Transmission becomes a proper noun, a name for an entity that took on a life of its own for a brief period in utility history.  But, in the end, Big Transmission had to die.
Picture
The author explains six points that make Big Transmission fail:
Big Transmission never did and never will make sense. Let’s look at a half-dozen reasons why: 1) the laws of physics, 2) higher reliability risk, 3) stricter contingency limits, 4) lumpiness and investment risk, 5) rigidity of source and sink, and 6) better alternatives.
 Concise explanation of each point is in the article, so I won't belabor them here.

But the purist in me simply can't overlook a couple of glaring errors.  First, the Figure 2 national transmission overlay map is mislabeled.  Existing and New 765kV transmission have their colors reversed.  The Existing 765 system is red on the map, and the New 765 system is green (the legend in the upper right is incorrect).  It makes a great, big difference when studying the map to figure out which lines are new Big Transmission and which lines are incremental existing builds.  Second, the author places the PATH project on the wrong line in the Figure 1 Project Mountaineer Map.  He says, "PATH was essentially the western half of the #2 project in the overall Project Mountaineer plan."  No, PATH was the western half of the #3 project in the Project Mountaineer map.  PJM's original Project Mountaineer called for a Big Transmission line from the John Amos power station to the Deans substation in New Jersey.  PJM combined several proposals into the Frankenstein monster that became PATH, and then cut it off at Kemptown, with plans to build a separate Big Transmission project from Kemptown to Deans at a later date.

But, other than those two mapping boo-boos, the article gets the demise of the PATH project exactly right.  The demise of PATH has been wrongly portrayed by many people, with claims covering everything from reduced demand to coal plant retirements.  In his note 29, the author correctly notes that the demise of PATH was a combination of factors:
It is difficult to apportion the demise of PATH among reduced load growth, the Mt. Storm-Doubs alternative, new generation, and sophisticated statelevel opposition. However, it is fair to observe that reduced load growth had only postponed PATH in the past (three times). What was different in 2010 was the emergence of the Mt. Storm-Doubs  alternative, and the focus of a state regulator on that alternative.
That's right... every factor, except Mt. Storm-Doubs, simply delayed the PATH project.  Mt. Storm-Doubs, and the "sophisticated statelevel opposition's" overwhelming support of this alternative to change the political climate supporting the PATH project, is what killed PATH.  Better, cheaper alternative that the people support?  It's the winning PATH of least resistance!

The realities of the "need" for PATH, and its opposition, merely delayed the project long enough for Dominion Virginia Power to step onto the stage with its proposed rebuild.  But even that wasn't simply about a better idea... the Mt. Storm Doubs line's existing towers were built out of a certain kind of steel that had not stood the test of time.  The tower bases were deteriorating and patchwork fixes were no longer effective.  The towers needed to be replaced before they started falling down.  And while they were replacing the towers, everything else got an upgrade that increased the line's thermal capacity 65% (allowing it to carry more power).  Dominion smartly took advantage of the PATH debacle to get its line rebuilt with minimal opposition, and even the outright support of affected landowners.

Would this situation repeat itself to kill other Big Transmission proposals?  Probably not.  But it does support the idea that incremental transmission projects and rebuilds are much easier to build than Big Transmission.  So, why does the utility industry continue to propose and/or support Big Transmission?  Because it comes with Big Profits and they're willing to risk protracted planning and permitting processes in order to increase their profits.  It's not about building reliability, economic benefits for consumers, or even "cleaner" power...  and all the risk of Big Transmission ends up on the backs of consumers.  What's not to like for them?  The facts in this article -- Big Transmission must fail.

There's even some hard truth about the last of the Big Transmission projects that have yet to realize they're dead.  Clean Line Energy came up with its idea to build thousands of miles of Big Transmission to ship renewables from coast to coast in 2009, when Big Transmission was in its heyday.  But, unlike utility proposals where risk and cost is shouldered by ratepayers, Clean Line has spent millions of dollars of private investment cash to keep its idea alive.  Once Clean Line gives up, its investors lose everything.  There is no federal guarantee to recover sunk costs on speculative, market based Big Transmission.  And Clean Line, itself, will die along with its projects, and its executives currently living high on the hog of private investor cash, will be in the unemployment line.  This is what keeps Clean Line on life support long after it's been pronounced brain dead.  And here's why Clean Line will never happen:
But certainly when Big Transmission is dependent upon market conditions the lumpiness and risk factors are all the more daunting. Big Transmission somehow needs to bring together generation resources and market demand – to the exclusion of alternatives – to forge a level of commitment that will last for many years. That’s a prerequisite for financing. So the entities at each end need to perceive such a compelling business proposition that they will forego other alternatives and cast their fate with Big Transmission. That’s a tough sell.

FERC requires that utilities interconnect all new generation. So a new generator is assured of being able to interconnect its project to the utility serving the territory it is located in; the issue is solely how much money and time it will take for the interconnection. Given this legally assured ability to access the grid through the resident utility, market-based Big Transmission is effectively competing with that utility and thus must offer substantial value added.
And there is no value added by a Clean Line.  Clean Line stupidly demonstrated just this point to the City of Hannibal, Missouri, earlier this year with its chart of wind options for the city.  The Clean Line prepared (and tweaked) chart showed that wind delivered over the existing incremental transmission system was just as cheap as wind delivered over a "clean" line.

Why would any company buy capacity from a risky new transmission line when existing lines are just as cheap?  This probably explains why Clean Line has no customers.  And without customers, Clean Line's Big Transmission will also fail.
1 Comment

Would You Trust This Guy?

5/23/2016

2 Comments

 
James V. Fakult needs to work on his communication skills.

I get lots of notices about new transmission proposals, but this one was so poorly done, it made me laugh out loud.  According to this article, liespotting is an art.  Watch out for number 6 when reading the quotes from Fakult.
Liars overemphasize their truthfulness. “To tell you the truth…” “Honestly…” “I swear to you…” Oh, if only it were so! When people use these bolstering statements to emphasize their honesty, there’s a good chance they are hiding something. Learning to baseline someone’s normal behavior is important in situations such as this:  You want to listen for normal or harmless use of such phrases. There’s no need to add them if you really are telling the truth, so be on guard.
Now listen to Fakult:
"The growth has been in some fits and starts, but we're at a point now where this is an essential project to continue to provide, really, the type of service, the level of service, that our customers expect from us," Fakult told the Asbury Park Press. "It reinforces the system in that area. It allows us to, again, provide better, more reliable, resilient service."
Really, James?  Really?  What was the purpose of sticking that word into your statement, except to bolster your statement that the people really need your project.  And you repeated yourself there at the end, hoping it would give more credibility to your proposition.  Clearly, he doesn't even believe it himself.  Maybe if he repeats it a couple dozen more times it will become true?
"The time is now," Fakult said. "It just needs to be done now."
Perhaps Fakult is attempting to tread carefully, since a substantially similar project was attempted many years ago but failed due to public opposition.
Nearly 16 years ago, the utility scrapped plans for a 6.5-mile transmission line, to be run on 60-foot high steel poles, along the railroad tracks from Matawan to Middletown, after intense community opposition. Residents and some town officials, fearing a reduction in property values and worried about health risks, fought the project for a decade.

"To me, it is nothing but a resurrection of precisely the same plan that we fought and stopped," said state Assemblywoman Amy Handlin, R-Monmouth, a vocal opponent years ago. "It's the phoenix rising from the ashes, it's the ghost of battles past. It's not different."
I don't think the people have forgotten.  Looks like opposition will be swift and fierce.  So, what's changed this time?
This time, the utility proposes to run the wires atop slender single poles that average 140 feet tall rather than bulky towers used in the past, spokesman Ron Morano said.
Who says the public likes monopoles any better than they like lattice towers?  Did AEP tell you that?
AEP isn't the public.  Truly aesthetic transmission is underground.  You should have started there, James.  Since everyone (214,000 ratepayers, according to the article) is going to benefit from the project, everyone should pay the increased cost of undergrounding it so it doesn't become a hazard or a burden to adjacent landowners.  You're always going to have opposition when you propose that a few should sacrifice themselves for the many.  Beneficiary pays.
The use of the NJ Transit corridor, which is already designated for public use and has existing electric infrastructure, as well as the slimmer monopoles, will help to minimize the disruption on the community, Fakult said.
Transmission lines are NOT like Lay's potato chips.  Just because someone lives near invasive infrastructure does NOT mean they want or deserve more of it.  Look at it this way -- those folks living in close proximity to existing infrastructure have already paid their dues to society.  Isn't it someone else's turn?
Morano, the JCP&L spokesman, said the utility follows all safety and heath guidelines and will have an electromagnetic fields expert available at open house sessions. "We are successfully building transmission lines in other (areas) without any issues," she said.
EMF health-related issues are entirely perceptual.  Your "experts" and selected 30 year old studies don't convince anyone.  How about putting your money where your expert's mouth is, FirstEnergy?  How about offering the landowner a written guarantee to cover the health care costs of any individual who can prove their illness was related to living in close proximity to your transmission line?  Your wallet clearly doesn't believe your "science."

So, next FirstEnergy plays its trump card to claim that PJM has determined the project to be necessary.
PJM Interconnection, the organization that oversees the electric grid in 13 states and Washington D.C., has identified the Monmouth County Reliability Project as a necessary project to reduce the length and frequency of outages in Monmouth County, the utility said.

If not built, "over the long term, you start to see issues emerge," Fakult said. "When you start to see peaking conditions, you just don't have the contingencies that you need to run the system reliably."
PJM?  The organization that "answers to no one?"  But your press release said YOU were proposing it, FirstEnergy.  Which is it?  Who first "identified" this project as a necessity?  Was it PJM, or was it FirstEnergy, looking to "energize" its profits by building transmission it believes necessary to meet future demand:
As noted in the fact sheet, Energizing the Future is a transmission initiative through 2017 that involves upgrading and strengthening the grid to meet the future demands of customers and communities. Key factors driving that investment include enhancing system reliability by replacing existing equipment with advanced technologies; meeting projected load growth; and reinforcing the system in light of power plant deactivations, the fact sheet added.
Fakult thinks he can do things differently this time:
The company plans to hold three open house events in neighborhoods near the proposed project to share information with the public and gather feedback. The company also is setting up a website at www.monmouthreliability.com.
You're going to hold three events guaranteed to thoroughly piss off the communities and give the opposition an opportunity to meet and greet and build mass, FirstEnergy?  You've really learned nothing at all over the years, have you?

Your talk about "need" really isn't convincing.  Did the utility "need" this transmission project the first time it was proposed, 16 years ago?  Obviously not, since it never happened and the lights still come on in those communities when people flip the switch.  Adding words like "really" this time isn't going to help you.

Once again, FirstEnergy puts its cart before its horse by presenting a community with a transmission project as a fait accompli.  Presuming the project is "needed" and it's only a matter of how to build it and where to put it will never be accepted at face value by a community.  First, you have to convince them that a need for something exists, and then you consult with the community to determine an acceptable solution.

That's true "community consultation."  Really.
2 Comments

Clean Lies About Iowa Ratepayer Benefits

1/13/2016

0 Comments

 
Do you often make a typo that turns "Clean Line" into "Clean Lie?"  Me, too.

Clean Line has a new shtick that claims Iowa ratepayers will benefit if the IUB allows it to change the process to make it less costly for its investors.  Clean Line's claim can be paraphrased like this:

If you don't make it easy for us to build the Rock Island Clean Line (RICL) using the merchant model that charges customers in other regions for the cost of the project, then the Midcontinent Independent Systems Operator (MISO) will order new transmission just like RICL and make Iowa ratepayers pay for it.

Clean Line must really think Iowans and their Utility Board are a bunch of rubes.  This argument fails on so many levels, and the reality is that building RICL could actually increase electricity costs for Iowans.

First of all, this is an apples to oranges comparison.  RICL is not at all like the transmission projects MISO may order to be built.  RICL's stated purpose is to export electricity from the MISO region to the PJM Interconnection region.  MISO generally serves midwestern states, while PJM generally serves eastern states.  RICL proposes to move large quantities of electricity generated in MISO into PJM, where it may be used by "states farther east."  RICL is not proposing to serve any customers in MISO, particularly in Iowa.  Contrast that to the transmission projects MISO orders.  MISO is concerned only with serving customers within its own region.  Therefore, any transmission projects MISO orders will be for the purpose of moving electricity around the MISO region for use by MISO consumers.  MISO would never propose a transmission project for the express purpose of exporting electricity to another region, and then turn around and expect MISO consumers to pay for it.

Independent System Operators and Regional Transmission Organizations (which are generally identical constructs) are quite parochial.  They are utility member organizations that exist to serve their own regional interests.  Interregional planning is extremely fragile, to the point of being non-existent.  This is because an ISO/RTO will generally utilize its own resources first, from a cost and reliability standpoint, before importing resources from another region.  RTO/ISO members would never agree to pay the cost of export to another region, and moreover, this rubs against the Federal Energy Regulatory Commission's Order No. 1000, that ensures that only beneficiaries pay the cost of transmission built to serve them.

Therefore, the building of RICL would have NO EFFECT on the transmission projects MISO orders to serve its consumers.  MISO will still order the transmission it needs to serve consumers in its region, including Iowa.  RICL is no substitute for MISO-ordered transmission because it would not serve any consumers in Iowa, or anywhere in the MISO region.  At best, RICL is agnostic about costs to Iowa ratepayers.  It certainly won't save them any money.

RICL may actually cost Iowans higher electricity prices.  Think of electricity produced in Iowa as a reservoir.  As long as supply is plentiful, prices remain cheap, and cheap energy is dispatched first to Iowans.  However, RICL would turn on a gigantic tap that drains that reservoir and sends the water (or electricity) to other regions with higher prices.  This creates an imbalance between supply and demand, where Iowa electricity buyers must now compete with other regions to buy the cheapest Iowa-produced electricity remaining in the reservoir.  Transmission lines levelize prices between electricity's source and sink (consumers), lowering prices in other areas by making cheaper energy available to new users, while raising prices at its source by increasing competition for the newly-limited supply.  Exporting a plentiful supply of anything raises local prices by lowering supply.  It's the simple principle of supply and demand.

Clean Line has come dangerously close to violating its negotiated rate authority granted by the Federal Energy Regulatory Commission.  FERC based its grant of authority, in part, on the following:

To approve negotiated rates for a transmission project, the Commission must find that the rates are just and reasonable. To do so, the Commission must determine that the merchant transmission owner has assumed the full market risk for the cost of constructing its proposed transmission project.

Rock Island meets the definition of a merchant transmission owner because it assumes all market risk associated with the Project and has no captive customers. Rock Island has agreed to bear all the risk that the Project will succeed or fail based on whether a market exists for its services.
What RICL proposed in Iowa is a shifting of risk to Iowans.  RICL believes it should not be subject to the financial risk presented by Iowa's long-standing permitting process that requires it to negotiate voluntary easements or prepare time-consuming Exhibit E material before being granted a permit.  Instead, RICL believes Iowans should be subject to a confusing, inconvenient, and more costly bifurcated permitting process in order to absolve RICL of any financial risk during the permitting process.  This is a shifting of financial risk to Iowans.

In its application to FERC, RICL talked big about sharing the risk with its customers, the load-serving entities (LSEs) that would buy its capacity.
Rock Island also argues that wind generators, whose energy the Project will likely transmit, present numerous risks that transmission project developers and investors must overcome. For example, Rock Island states that wind energy projects are typically constructed with shorter lead times than other generators and are less willing to commit to large transmission projects well in advance of generator construction. Rock Island argues that pre-subscription of capacity with creditworthy anchor customers can reduce financing obstacles because lenders demand to see a secure source of revenue as a predicate to project financing.
Here, it appears that RICL is suggesting that it can sell its capacity to LSEs before the project is built.  These entities with a guaranteed spot on RICL's wind highway would later buy electricity from wind farms connected to RICL.  Not only would it lower RICL's financial risk by providing the company with capital before its project is online, it would also provide a future revenue stream that wind farms could use to secure their own financing.  Perhaps RICL should be looking to share its financial risk in Iowa with its potential customers by pre-subscribing its capacity to LSE customers at this time?  Let the LSEs pony up the funds necessary to negotiate voluntary easements or create Exhibit E materials.  That would shift the financial risk from RICL to its customers, where it belongs, instead of to Iowans.

Except RICL doesn't have any customers.  Potential customers have been unwilling to shoulder any of RICL's financial risk during the permitting process.  Chicken/egg.  This demonstrates why Clean Line's business model will never work unless states agree to shift Clean Line's risk onto their own citizens by permitting a project that has no customers.  Iowa said no on Monday.  Arkansas said no in 2011.  Missouri said no last summer.

In order to hide its failure to share risk with its own customers, RICL whined that the Iowa process is flawed and must be changed to shift risk from RICL to Iowans.

I'm not buying it.  How about you?
0 Comments

Clean Power Plan Does Not Require "A Tangled Mess of Hulking, Long-range Transmission Lines"

1/12/2016

3 Comments

 
The Pittsburg Post-Gazette's "Power Source" energy news believes the Clean Power Plan will require "a tangled mess of hulking, long-range transmission lines."  Not true, and the report's "facts" are fallible.

The reporter seems to rely on energy platitudes, pasted together with quotes from people who should have been asked about the conclusions the reporter made.

Such as:
Opponents used some of those arguments to successfully derail the Potomac-Appalachian Transmission Highline, a 290-mile line from Putnam County, W.Va., to Frederick County, Md., proposed by Allegheny Energy in 2008. The Greensburg company, acquired by FirstEnergy in 2011, suspended the project after it could not convince regulators the line was necessary.
This guy calls up Steve Herling, but doesn't bother to ask him why PJM terminated the PATH project.  It's not that "opponents" proved there was no need in any state regulatory process.  It's that PJM first suspended, and later terminated the PATH project because
PJM staff reviewed results of analyses showing reliability drivers no longer exist for the project throughout the 15-year planning cycle. The analyses incorporated the continued trends of decreasing customer load growth, increasing participation in demand response programs and the recent commitment of new generating capacity in eastern PJM.
This reporter also seems to be under the impression that all transmission opposition comes from "citizens groups" who oppose transmission due to environmental reasons.
While citizen groups have fought transmission projects — often successfully — by attacking the developer’s need to build them, the environmental regulations could usher in more projects and complicate opposition.

Changing drivers of transmission
In the past, environmental groups have glommed onto transmission battles and used citizen group opposition to fuel the push on environmental grounds.  Those days are over.  This reporter seems to be the last to find out, but environmental groups are the newest and biggest fans of transmission lines.  Numerous environmental groups have intervened in favor of big, new transmission lines that the wrongly believe are "for wind."  Transmission lines are open access and it's not possible to segregate "clean" electrons from "dirty" ones.  The citizens are on their own here and that's just fine... nobody needs or wants a hypocritical environmental NGO championing eminent domain for "clean" transmission lines while simultaneously using the same issue as a reason not to build "dirty" pipelines.  Nobody takes these fools seriously anymore.  Without an army, the environmental groups are simply Don Quixote.  Tilting at their beloved windmill fantasy, but getting nothing accomplished.

It's still about need though.  And the transmission poster child the reporter chose to use is not part of any regional transmission plan and therefore has not been designated "needed."
Transmission companies see big potential for new projects, particularly from sparsely populated areas that generate wind energy to urban areas. “Just as trains carried cattle and other goods from the rural areas to urban centers, the Plains & Eastern Clean Line will carry renewable energy from the Plains of the Southwest,” states the website of one developer, Clean Line Energy of Houston, Texas.

Clean Line expects federal approval for its 700-mile Plains & Eastern Clean Line, designed to carry 4,000 megawatts of power from wind farms in the panhandle of Oklahoma. The line will terminate near Memphis, Tenn. Clean Line has four other projects in the pipeline.

“We anticipate a very busy 2016,” said company president Michael Skelly. 
And that's why Clean Line is attempting to use an untested part of the 2005 Energy Policy Act to usurp the siting and permitting authority of states and ram its project through using the federal eminent domain authority of federal power marketers.  Except that statute requires a need for the transmission in the first place.  And there is none.  Clean Line elected not to participate in the regional transmission planning processes that determine need for transmission projects.  Clean Line is nothing but a gamble -- the investors are gambling that a need for the project will develop if they can build it... but Clean Line hasn't been successful in signing up any potential customers... because they can't get their project built... because there is no need for it.  That's the real chicken/egg the reporter should be examining.

I do hope Mr. Skelly is very busy in 2016... polishing up his resume and looking for new investors for his next get rich quick scheme.

The reporter longs for
...some wind mills and solar farms in areas with constant breeze and abundant sunshine
But he's looking in the wrong place.  Even though he had a conversation with Scott Hempling about non-transmission alternatives, none of that seemed to sink in.

There's an area with "a constant breeze" located much closer to Pittsburgh than the Great Plains.  It's called the Atlantic Ocean, where wind potential is much greater.  Best of all, very little "
tangled mess of hulking, long-range transmission lines" would be "necessary to bring that renewable power from the point of generation to utilities for local distribution."

Why can't eastern states boost their own economies by harvesting renewables close to load?  The days of centralized generation are over.  Also, sunshine is abundant anywhere -- no transmission lines needed to slap some solar panels on your own roof.

This reporter needs some education.

1.  Transmission opposition by "citizens groups" won't change because of the Clean Power Plan.

2.  Speculative transmission projects for which there is no need shall not be granted state eminent domain authority to take property for rights of way.

3.  Clean Line is a merchant transmission project, not part of any transmission plan and completely unlike most other transmission projects.  Therefore, it should not be lumped in with them or used as an example of anything transmission-related.  If the CPP requires transmission, it will be planned and ordered by regional transmission organizations so that there is some surety that it will actually be built.  Clean Line is not needed, may never be built, and is driven by anticipated profits selling energy into more expensive markets, not by the Clean Power Plan.

And stop drinking the big wind koolaid.  There are no facts in it.
3 Comments

Dominion Enticing Virginians With Their Own Money

1/6/2016

0 Comments

 
Looks like Dominion has finally reached the bottom of the barrel in its desperate attempts to get approval for construction of a 500kV transmission line across the James River at Jamestown.

An article in the Virginia Gazette says that Dominion is now offering $85M in "mitigation" to groups opposing its project.  The $85M includes:
The mitigation proposal includes more than $52 million in funding for Jamestown Island, Hog Island and the Captain John Smith Historic Trail District. The money would fund projects such as seawall rehabilitation and replacement at Historic Jamestowne to help combat the impacts of sea-level rise and erosion, according to the draft mitigation plan obtained by the Virginia Gazette.

The mitigation plan proposal includes $15.5 million in funding for water quality improvement including erosion and sediment control in the James River. Battlefield and landscape conservation projects would get $12 million, including government and private lands associated with the Battle of Yorktown, according to the proposal. More than $4 million would go to protecting emergent marsh at the Hog Island Wildlife Management Area.
But here's the thing... the $85M in blood money would be paid for by electric ratepayers in PJM Interconnection's 13-state region, not by Dominion.  That's right, Dominion's "generous" offer would become part of the capital costs of its Skiffes Creek project, which will be reimbursed to the company through federal transmission rates over the 40-year life of the transmission line, plus interest.  Paying off the capital cost of a new transmission line works much like a mortgage, where a small amount of principal is paid each year, in addition to interest on the remaining balance.  Dominion's "interest rate," called return on equity, is currently set at 11.4%, annually. 

What Dominion is offering is that YOU will pay to "mitigate" the destruction of YOUR historic resource.  And Dominion will make a profit on the deal.

And, really, would $85M of unrelated improvements to the Jamestown historic area make the new transmission towers in the James River disappear?  No.  No matter how much of your money Dominion throws at it, the transmission line will still forever spoil historic Jamestown.  At the end of the day there will still be a transmission line in the river.  The $85M isn't "free" money coming out of Dominion's coffers, it's money that will be added to your electric bill for the next 40 years.  Aren't there better ways to pay for improvements to Jamestown than through a backdoor fee on your electric bill that also includes a hefty profit for Dominion?

Dominion's price for the transmission line is $155M, before "mitigation."  With mitigation of $85M, the new total for the project's capital costs is $240M, a substantial cost increase.  Don't you think Dominion could put that $85M to work finding a better solution to its plan, such as undergrounding the transmission line? 

And here's the best part... if Dominion is denied a permit to build its current project, then PJM must go back to the drawing board to find another solution to the supposed reliability issue.  Any new solution must now be competitively bid, not just handed to Dominion to build, as the original project was many years ago.  Competition is always a good thing, and will most likely result in a better, cheaper, "constructable" solution. 

Just say no to Dominion's ratepayer-funded blood money and send this project back to PJM's drawing board.
0 Comments

Willful Blindness and Propaganda

1/3/2016

0 Comments

 
A Virginia blogger visited PJM Interconnection to find out who they are and what they do, and then wrote about it.  That's great investigative journalism because only a handful of the 61 million electric consumers served by PJM even know it exists.  However, I do wish the blogger had a bit more curiosity to scratch underneath the surface of some of PJM's propaganda.

Amid a factual account of how PJM operates, I found this thoughtless propaganda blurb:
Electricity on the PJM grid normally flows from west to east. The major centers for electricity demand are the big metropolises along the Eastern Seaboard, at the eastern edge of the PJM system. There aren’t any power plants located in the Atlantic Ocean, therefore power that isn’t generated locally has to come from the west. As it happens, PJM’s western states have abundant, low-cost wind power — at night-time, wind power is so plentiful compared to demand that the price essentially falls to zero. The main factor limiting East Coast access to that cheap wind is the limited capacity of the transmission grid to carry it.
There aren't any power plants located in the Atlantic Ocean, but it's not due to lack of a "low-cost" source of energy.  Offshore wind is a better source of energy than land-based wind.
In the United States, 53% of the nation’s population lives in coastal areas, where energy costs and demands are high and land-based renewable energy resources are often limited. Abundant offshore wind resources have the potential to supply immense quantities of renewable energy to major U.S. coastal cities, such as New York City and Boston.  

Offshore winds tend to blow harder and more uniformly than on land.
Why would PJM, a member organization of power producers and distributors, downplay the viability of offshore wind, if it is truly "agnostic about the desirability of renewable energy?"  Is it because PJM has an interest in building more transmission to expand its empire, or simply an interest in protecting the interests of its members?  Or did this propaganda form in the mind of the blogger?

In Virginia, Dominion Power controls offshore wind energy development.  And some believe Dominion is dragging its feet.  Why would they do that?  Dominion says its because the cost of offshore wind development is too high, but I think it's a simple matter of milking old technology for the most profits before embracing new ideas.

While Dominion whines that building two test turbines off the coast of Virginia Beach will be too costly at a price of up to $400M, another company is proposing to build new transmission to bring Midwest wind energy to coastal cities at a cost of $8.5B.  Yup, that's billion. 

Something doesn't make sense here.  Let's crack this nut. 

Energy flows from west to east in PJM based on history.  Over the past 100 years, Ohio Valley coal producers have been only too eager to plunder Appalachian states for their natural resources for benefit of those eastern metropolises.  The coal was mined and burned in the Ohio Valley, while the electricity produced was shipped east via gigantic transmission lines.  It worked because powerful interests in the Ohio Valley were happy to destroy local environments in exchange for the economic benefits of serving as an "energy exporter."  The eastern cities got the benefit of "cheap" Appalachian energy, without having any of the pollution or environmental destruction in their own backyard.  And they liked it.  And they got used to it.  And they expect it.  But, the times... they are a'changing.


Coal is no longer king.  Eastern cities are clamoring for "renewable" energy.  And while entrenched interests like Dominion cling to dirty energy sources in order to milk every last dime from them, other powerful interests have set their sights on the Midwest as a new source of energy exports.  There's money to be made hyping America's breadbasket as "the Saudi Arabia of wind" and building billions of dollars worth of new infrastructure to continue the status quo of west to east power flows.

But, unlike the Appalachia of 100 years ago, Midwestern landowners are having none of the sacrifice that goes along with being energy exporters.  While a handful may be content to voluntarily lease land for wind turbines and collect royalties
, the vast majority will not gladly sacrifice their homes and businesses to host gigantic new "energy highways" to ship electricity thousands of miles to eastern states like Virginia.  These businessmen and women realize there's nothing in it for them, as "market value" payments for easements through their food factories do not adequately compensate for loss of production.  Adding insult to injury, while land leases for wind farms are voluntary (and subject to free market negotiation), easement purchases for transmission lines are proposed to be involuntarily accomplished through eminent domain.  Landowners are faced with voluntarily jumping off a cliff before they are pushed over the edge.  This isn't a choice, and "market value" has little meaning when there is no choice.  There is no "market" for involuntary land sales.

You simply cannot continue the west to east energy flow status quo, Virginia!  It won't end up being "cheap" plowing through thousands of miles of productive farm land with new infrastructure in order to bring you "cheap" wind energy.  The days of rural America to your west gladly sacrificing for your needs are over.  If you want clean energy, make it yourself.   Stop telling yourself that Midwest wind energy is your next Appalachia.  It's just as expensive and it requires sacrifice from people who receive no benefit.

Instead, why not encourage Dominion (and their transmission minion, PJM) to develop the wind energy resources in your own neighborhood?  The extensive transmission system
required to transmit offshore wind energy to eastern cities is already in place, saving billions of dollars worth of new infrastructure.  As well, a plan for an offshore transmission backbone to collect offshore wind energy and transmit it to shore at several crucial points has been in the works for years.

Stop drinking the industry koolaid that convinces you that you're helpless, Virginia.  Create your own vibrant energy future
in your own backyard!
0 Comments

Requests for Rehearing Filed in ICC Grain Belt Case

12/16/2015

0 Comments

 
On Monday, the Illinois Commerce Commission was hit with an onslaught of Requests for Rehearing of its Order issuing a Certificate of Public Convenience and Necessity to Grain Belt Express.  Even Clean Line filed one!

The majority of the requests focus on the Commission's error in allowing GBE to utilize the expedited permitting process reserved for public utilities.  Grain Belt Express is not a public utility.

Rehearing requests came from:

Concerned Citizens & Property Owners.  CCPO concentrates on the expedited process error.

Illinois Farm Bureau.  Farm Bureau concentrates on the expedited process error and additionally contends that the project is not the least cost option.
GBX is asking for a back-up plan for its field of dreams approach to recovering costs, by coming back to the Commission to comply with the financing condition proposed in the Final Order.
GBE does not have the capacity to manage and supervise construction of the project, nor the ability to finance it.  Farm Bureau contends that issuance of the CPCN is premature.  It also believes that the actions of the Missouri PSC make GBE moot.
As the Farm Bureau previously argued before this Commission, the denial of GBX’s Application by the MPSC, along with the recent Circuit Court of Caldwell County Order which held that GBX has no authority to construct the proposed line through Caldwell County, Missouri, there will be no construction in Illinois by GBX due to the denials in Missouri. This Commission should consider additional evidence on this issue which occurred after the close of the evidentiary hearings, as described in Exhibit A, the Affidavit of Paul A. Agathen, a Missouri attorney who represents the Missouri Landowners Alliance (“MLA”). The Final Order erred on this issue. Thus, the Commission should rehear this issue.
The Illinois Landowners Alliance request parallels the Farm Bureau's, and adds that the Commission erred in its finding that GBE would promote the public convenience and necessity and promote the development of a competitive electricity market.  It also contends that the permit will "create an immediate cloud and deprivation of property rights which the landowners along the 200-mile route would experience for an unknown period of time."

Grain Belt whines that the Commission made an error when it said, "The Commission finds that GBX has not demonstrated that the Project is needed to provide adequate, reliable, and efficient service to customers within the meaning of Section 8-406.1."  Sounds good to me!  What's not to like?  GBE also gets its panties in a wad over the fact that the Order did not specifically mention the 345-kV facilities running from the converter station to the substation in Indiana.

But... I've saved the best for last.  Read this one slowly and savor it like a tasty after dinner mint.  The request for rehearing of Mary Ellen Zotos is a knowledgeable, entertaining look at the bald truth of GBE and points out all that is plainly ridiculous about GBE and the ICC's Order.  This attorney is awesome!  What separates a good attorney from a great attorney his command of written language, and this request contains enough zingers and snark to fuel a thousand anti-Clean Line Facebook posts.  Here's just a few snippets:
The record in this docket is devoid of any evidence that the Project would promote the convenience or necessity of anyone other than GBX and certain West Kansas wind developers who said they would use the Project if it ever gets built.

Boiled down, GBX merely asserts that a beneficial project like the Project is needed. Why is it needed? Because it is so beneficial. GBX’s argument that a need for the project exists based on a set of alleged benefits amounts to question-begging on a grand scale. GBX assumes what the Commission should require it to prove. Rather than focus on whether there is any need for the project, GBX jumps right into a show-and-tell on how beneficial the Project will be. The Commission concludes from this that a project with this many benefits must be needed.

Stated another way, the Commission fails to distinguish a benefit from a need. It merely accepts GBX’s catalog of purported benefits as proof of need. Under the Commission’s look-only-at-the-benefits logic, it could just as easily conclude that residents of Point Barrow, Alaska need Frigidaires.

...the Illinois RPS may be satisfied by buying RECs generated in GBX’s targeted west Kansas resource area, and those west Kansas-generated RECs can be purchased without having to build a $2,750,000,000 transmission line across four states.

...the GBX Project is “[l]ike that old 1970s song about Oz and the Tin Man, [because GBX] will give nothing to PJM that it doesn’t already have.”

While the Commission makes soothing noises that it takes seriously the landowners’ concerns about GBX’s ability to use the power of eminent domain against them, it immediately and blatantly contradicts itself by dismissing their concerns as unwarranted because GBX has not specifically requested eminent domain authority in this docket.  Less than a moment’s thought suffices to show the absurdity of the Commission’s position on this issue. If GBX is granted a CPCN it could ultimately use the power of eminent domain against landowners under Section 8-509.
Instead of coming to grips with the power of eminent domain as an integral component of public utility easement acquisitions, the Commission adopts the Pollyanna Principle and accepts at face value GBX’s well-oiled talking points about its voluntary “code of conduct” when dealing with landowners, its promises of respectful treatment, its commitment to negotiate reasonably, and so forth. For the Commission to completely discount the potential impact of eminent domain on landowners simply because GBX did not ask for it in this docket is arbitrary and capricious, and an utter abdication of the Commission’s duty to Illinois citizens.

The Commission’s attitude toward GBX is one of serene and nearly limitless benevolence: whatever GBX can’t do now, it can certainly do later. The Commission will grant GBX its CPCN here and now even though it can’t satisfy most of the requirements of Section 8-406.1 until some unknown point in the future.

But when the landowners raise the issue of GBX’s potential future use of the power of eminent domain against them, which the Commission knows full well inheres in every easement negotiation between GBX and a landowner, the Commission summarily dismisses their concerns as premature because GBX hasn’t asked for eminent domain power here and now, in this docket. In this the Commission subjects the landowners to an egregious double standard, and indulges itself in arbitrariness and caprice of the grossest sort.

GBX’s least cost argument thus rests entirely on its claim that it has no alternative but to be least cost because its entire corporate existence will be some kind of Darwinian
market struggle where only the fittest survive.

The unmistakable irony here is that GBX destroys its own claim to be least cost by asserting that it can exempt itself from those same inexorable free market forces if the going gets tough: GBX reserves to itself the right to seek cost allocation to ratepayers, and in so doing proves itself just another corporate dissembler trying to evade committing itself irrevocably to the ups and downs of the market. And if there are too many downs, the ratepayers can bail GBX out.

But in this docket GBX tells the Commission that it is a “merchant transmission owner” not because it has assumed the full market risk of the Project, but because it plans to earn revenues through discrete transmission services contracts with shippers. This definition of “merchant” transmission owner” appears nowhere in FERC’s orders. That’s because it is a definition concocted entirely by GBX itself, and it differs fundamentally from FERC’s.

Understanding the term “assumption of all market risk” does not require a degree in economics: an assumption of all market risk means exactly that, all market risk, come Hell or high water.

This Commission has no jurisdiction to determine whether or how much of an interstate transmission operator’s costs may be recovered from anyone. The rates, terms and conditions of service for interstate transmission are exclusively matters of federal jurisdiction.

...GBX has no power to confer on this Commission subject matter jurisdiction over the rates, terms and conditions of service on interstate transmission facilities.

If GBX were really a “merchant” transmission owner as defined by FERC, then there would be no questions concerning cost allocation,
and this entire discussion would be unnecessary. GBX simply wants to have it both ways, eating its free market cake while having its cost allocation too.
I hope you enjoyed that as much as I did!   The attorney who wrote it, Paul Neilan, also writes a blog.  If you enjoyed that filing, you'll probably enjoy the blog as well.

The ICC now has 20 days to consider the requests and make a decision to either rehear the case or deny the requests.  If the Commission denies the requests, the litigants can proceed to court appeals.

Things are definitely heating up in Illinois!  More fun to come!
0 Comments

FERC to "Further Consider" PATH's ROE Rehearing Request

12/15/2015

1 Comment

 
The Federal Energy Regulatory Commission has added reconsideration of PATH's request for rehearing of the Commission's denial of its RTO membership incentive adder to the agenda of its monthly meeting scheduled for Thursday.

It's been so long since the Commission granted rehearing on this limited matter, it's been nearly forgotten in the ensuing shuffle.

At issue is PATH's request to continue to collect a half a percent of extra incentive return on equity for its membership in PJM Interconnection.  When the Commission granted PATH a whole bunch of incentives back in 2008, it also granted it an additional 50 basis points for joining PJM.  PATH proposed that it be allowed to continue to collect this incentive after it abandoned the PATH project, by continuing its membership in PJM until it had finished collecting its abandoned plant.

The Joint Consumer Advocates answered PATH's request for rehearing, and pointed out that the stated purpose of section 219 is to provide incentive-based rate treatments that benefit consumers by ensuring reliability and reducing the cost of delivered power.
  The PATH project has not benefited consumers by ensuring reliability because it was never built.  And it certainly never reduced the cost of delivered power.  Quite to the contrary, PATH increased the cost of delivered power by leaving ratepayers on the hook for its $121M of development costs even though it never even put a shovel in the ground.

In other words, even though PATH will never be built, and the PATH companies will cease to exist as soon as their abandoned plant is collected from ratepayers, PATH wants to be financially rewarded for continuing its pointless membership in PJM.  A membership in PJM allows the member to participate in the PJM transmission planning process.  Since PATH won't be built, and since the PATH companies were single purpose entities that will never plan or build another transmission project, what's the point of their continued membership in PJM?

I think the point is to continue to collect an additional half a percentage point of return (or interest) on the slowly dwindling $121M abandoned plant balance that PJM ratepayers must pay for.

It will be interesting to see what the Commission does to dispose of this matter.
1 Comment

FirstEnergy Wants Backroom Deal That Kills Competition in Ohio

12/7/2015

2 Comments

 
Have you been paying attention to FirstEnergy's backroom deal charlie foxtrot in Ohio? 

The company has proposed to regulators that Ohioans be forced to buy all the power produced at its unregulated ("competitive") Davis-Besse nuclear and Sammis coal-fired power plants at a fixed price that guarantees FirstEnergy a profit, and then sell the power into the PJM electric market.  The impetus here is that power prices in the PJM market have been low.  Competition was working to save ratepayers money!  However, competition wasn't making FirstEnergy enough money, so FirstEnergy has been busy stashing its competitive generators into state regulated environments where the company could be guaranteed a certain profit.  Have no doubt that once power prices recover and FirstEnergy has a chance to make more money competing to serve customers, that it will find a way to once again deregulate these power plants and keep the profits.

In addition to the current Ohio fiasco, FirstEnergy's competitive arm successfully "sold" its Harrison power station to regulated  West Virginia customers several years ago at a huge profit.  The ratepayers will hold the losses from the cost of operating this plant until such time as it once again starts generating a profit.  Then FirstEnergy will probably propose to sell it back to itself at another huge profit.  Although the West Virginia plan was hotly contested, all the opponents (except for the West Virginia Citizens Action Group) folded at settlement, content to accept cheap gifts in exchange for their support of the sale.

Not so in Ohio.  The opponents are sticking to their guns and have rejected a backroom settlement deal crafted between FirstEnergy and the staff of the Public Utilities Commission of Ohio.  Not that FirstEnergy cares... it's content to reach a settlement with a few parties who appreciate their cheap parting gifts.  Whatever it takes to secure FirstEnergy's profits in a noncompetitive environment.

When will this nonsense end?  Along with a plethora of stories about the deal (here and here, for example) came another story about FirstEnergy's stock price going up... directly tied to the backroom settlement:
The purchase power agreement (PPA) [with Public Utilities Commission of Ohio] was the last missing piece: balance sheet shored up; equity overhang removed — we see no more surprises for investors.
So, it's more important to protect investors with continued stock dividends than it is to protect the customers who need a public service? 
"FirstEnergy’s proposal will put safeguards in place to protect our customers from increased price volatility that’s expected to occur in the years ahead," said Doug Colafella, a company spokesman.
Oh, really?  I suppose the stock price increase and urge to buy FirstEnergy is just unrelated serendipity?  What a shyster!

FirstEnergy's plan is to remove any threat of competition to its generating plants, ensuring they can thrive in a lower-priced market by using captive ratepayers to provide market power through subsidies.
... other utilities will want profit guarantees in Ohio and in neighboring states. This, in turn, will undermine a competitive market in which many companies do not have the resources to secure government help the way that FirstEnergy does.

Independent power companies competing against FirstEnergy for customers in Ohio and throughout the 13-state region where high-voltage transmission lines are controlled by PJM Interconnection are not asking for special deals like FirstEnergy is, said Glen Thomas, president of PJM Power Providers Group.

"Our members are competing to provide the most efficient and economic power to consumers in Ohio as possible. We oppose this deal.  We see it as destroying all the benefits Ohio has gained from competitive markets.

"By going down a road where you subsidize plants that are not able to compete economically with other plants, you crowd out these economic advantages as well as send a terrible signal to the market that the best way ... is not to operate at most efficient levels but to seek a bail out from the PUCO."
But, wait a sec... I thought PJM's power markets were "competitive."  Market Monitor Finds PJM Wholesale Electricity Markets Competitive.  Is the Market Monitor paying any attention to what's going on with FirstEnergy's noncompetitive stashing of its competitive generators into regulated environments in order to gain advantage over competing generators?  Or is it too busy trying to claw back payments its stupidly designed markets made to some trader foxes, while ignoring the noncompetitive behavior of certain chickens in its market hen house?

This whole debacle is a lesson in the stupidity of allowing for-profit companies to provide a necessary public service in a monopoly market.  Because investor profit that powers big salaries and sweet perks for utility executives will ALWAYS outweigh any obligation to customers.  And big utility profits fuel backroom deals like the one proposed in Ohio.

I hope the Ohio opponents, such as Sierra Club, continue to call foul on this deal and don't knuckle under and give in like they did in West Virginia.  Integrity is a valuable commodity in the market of real life.
2 Comments

Powhatan v. FERC:  Showdown at the U.S. District Court Corral

11/10/2015

2 Comments

 
The U.S. District Court for the Eastern District of Virginia looks like the O.K. Corral in the aftermath of the recent paper showdown requesting dismissal of FERC's petition to request an Order Affirming the Commission's Order Assessing Civil Penalties of $34.5M against defendants Powhatan Energy Fund and Alan Chen.

On October 19, Powhatan and Heep Fund, et. al. (Chen defendents) filed Motions to Dismiss FERC's request prior to trial.

The Powhatan Motion to Dismiss relies on FERC's failure to provide fair notice that the trades at issue were illegal at the time they took place.  Powhatan says this raises serious due process issues.

The Heep Fund Motion to Dismiss relies on a contention that the statute of limitations had expired before FERC's filing in U.S. District Court for all but 4 days of the subject trading.  Heep Fund also says that the complaint does not state a claim for market manipulation.  They also claim the same due process issues raised in Powhatan's Motion.  And, finally, Heep contends that the FPA does not authorize manipulation claims against individuals like Dr. Chen.

FERC responded on October 30, claiming Fair Notice precedent supports their claim and that Powhatan mischaracterizes the Commission's actions and precedent, and that none of their claims have merit.  FERC's response to Heep Fund made similar claims that their Motion to Dismiss was all wet.

What I found interesting here was FERC's reading of its Black Oak precedent as recognizing that traders may make trades solely to capture MLSA payments, however FERC "fixed" that problem by requiring traders to also purchase transmission.


In March 2009, PJM followed the narrower approach, proposing to pay MLSA to all trades with paid transmission (physical or virtual). In response to that filing, no party suggested that UTC trading would be susceptible to the kind of perverse incentives that the Commission understood could apply to most virtual trades.

No party filed any comments rebutting this contention as to the narrow distribution method, and the Commission accepted it in September 2009. Black Oak Energy, LLC, et al. v. PJM Interconnection, L.L.C., 128 FERC ¶ 61,262 (2009).
So, the Commission believed it had closed any loophole that created an incentive to place trades with the intention of collecting MLSA payments by requiring traders to purchase transmission.  But it didn't.  And the trading happened.

FERC contends, nevertheless, that the trading was an illegal type of trading, and in an effort to build a villain it uses the word "Enron" 19 times.  Everybody knows that Enron was bad, right?  And because this whole issue is so technical and hard to think about, maybe people will just go with the bad aura created by glittering generalities?  Here's another:  FERC used the words "Death Star" 17 times.  No average Joe knows what "Death Star" trading is, but it conjures up images of our Star Wars heroes being in jeopardy.  And it sounds really, really bad!!

FERC also prattles on about the Powhatan & Chen defendant's trading depriving other market participants of MLSA payments they would have scored if the defendants didn't trade.  But in this alternate universe where the defendants didn't trade, might others have traded instead, which would throw off any entitlement to MLSA payments by the other market participants?  And FERC has still failed to convince me that the MLSA payments would have flowed through to the electric rates paid by customers of the other market participants, instead of into the corporate coffers that pay share dividends.  Since FERC can't explain this properly, it must not be true that the other participants failure to receive MLSA payments caused higher rates for electric consumers.  I'm still waiting here...

Yesterday, Powhatan and Heep filed Rebuttals to FERC's responses.

Powhatan pointed out that FERC has changed its position on what the Black Oak orders meant, and "misses the forest for the trees."  Powhatan also points out a gap in FERC's logic:  If the Black Oak orders prohibited the trading at issue, why did FERC find it necessary to change the tariff to prevent this kind of trading AFTER it discovered what the defendants had done.  By closing the barn door after the horse got out, the Commission can now only retroactively fine Powhatan for trading that wasn't illegal when it happened.  And, of course, that idea is preposterous.

The Heep Rebuttal also refuted FERC's contentions in its Response.

So, now we'll see if the rocket docket
blasts off towards the Death Star, or dismisses this case, once the smoke clears in the corral.
2 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.